2025-02-17
In January 2025, in the factory of Dongqi Standard Parts, a set of 800kw/1720kwh BESS lithium battery energy storage system provided and installed by Zhitai (ZT-TEK) New Energy officially entered the commissioning stage.
A total of 8 liquid-cooled 100kw / 215kwh BESS cabinets are connected in parallel
Built-in liquid cooled air conditioning provides better cooling effect and higher IP protection level
The 3.2V 280Ah lithium iron phosphate cell developed and produced by ZT-TEK is adopted. The cycle life is more than 8000 times and the charging and discharging ratio is 0.5C
Intelligent BMS and EMS system, safely and flexibly adjust the charge and discharge scheme, to help customers better save electricity costs.